Project Duration

28
Days

Project Background

This commercial pool was located by the seaside and was timed for the quiet winter months when visitor numbers are low, making the project timeline a tight one. The remedial repair was required due to severe leaking and salt precipitation.

Problems we met

Within compressed 4-week timeframe, our team had to finish several tasks which included rendering, waterproofing, tiling by using epoxy adhesive, epoxy grouting, siliconing and cleaning. In addition, there was a high number of rain weather events.

Solution & Result

Based on the agreement reached with the construction company and local council, we arranged a schedule which used three teams working 24-hr shifts to provide 24/7 coverage in order to increase work efficiency. Along with the cooperation of the construction company and our customer, we finished the project on time.